Zero Scale Pit

text
Danieli offers the innovative solution of ZSP ™ - Zero Scale Pit technology to replace the standard conventional scale pit with reduction of civil works and execution time and simplify the access and maintenance of the pit.

The tangible advantages are saving of excavations, less civil concrete, less capex investment, fast project schedule and simplified maintenances activities. 

 ZSP solution

 Conventional scale pit system

 Waters coming from the direct cooling of rolling mill
 line are separated as different fluxes: fluxes
 containing big/heavy scale are sent to scraper
 conveyor packages while flux containing only small/
 light scale is collected in a separate pit and pumped
 directly to the longitudinal clarifier.
 All waters coming from the direct cooling of rolling
 mill line are sent to the scale pit to allow the big/
 heavy scale separation.
 The scraper conveyor packages and the pumping
 pit are located under/next to the rolling mill,
 consequently the concrete works are not so depth
 (-5 / -7 m).
 The scale pit unit collecting all water from contact
 circuits is located outside the building, because
 of the depth required (-10 / -15 m).
 The scale is removed continuously by the chain
 scrapers of the Dan-Dredge™.
 The scale accumulated in the pit is removed
 periodically by an automatic bucket.
 Time required for the execution of civil works
 is limited (about one month).
 Time required for the execution of civil works
 is considerable (about six months).